Fed Ex Exterior Building View, used for a project showcase of Squared Circle

Case Study

Fed Ex heating and comfort cooling upgrade

CDM Principal Design Services

Background

In October 2023, FedEx began planning an upgrade to their heating and HVAC systems throughout the main building at their UK Headquarters.

It was a complicated project, involving the installation of new fan coil units and pipework, and the removal and replacement of pipework for the cooling system.

Installation of a Mitsubishi VRS Refrigerant system was needed, as well as new roof mounted condenser units and Building Management System.

Challenges

Solution

Our CDM Principal Design Service provided solutions, addressing each of these challenges and ensuring all activity remained safe and compliant.


A phased works programme was designed, decanting staff to other areas and home working environments on a floor-by-floor basis, enabling clear and unrestricted access to areas of work.


To maintain building security, we created a secure external compound with a designated gated entrance from the main gatehouse. This was controlled by the main contractor, segregating works and deliveries from FedEx site operations to ensure the highest levels of security were maintained.


We provided a detailed Fire and Emergency Plan for the construction works, including temporary isolation of the fire alarm system in work areas. Out of hours monitoring and unrestricted temporary means of escape were also provided for remaining building users, when existing escape routes were closed off due to works.

Results